Belgian Authorities Order Google to Halt Data Centre Construction

Belgian regional authorities ordered Google to halt construction of a data centre in Farciennes after inspectors found workers finishing a three-hectare building without a valid planning permit.

Google Halts Farciennes Data Center Construction

Google has suspended work on its data center project in southern Belgium “pending additional guidance,” the tech company said after regional inspectors visited the 50-hectare former mining area. Nicolas Yernaux, a regional government spokesperson, told Agence France-Presse that inspectors observed a major offence involving the “illegal construction of a building covering three hectares.”

Google originally secured a permit in 2024 to build three air-cooled facilities on the property. In 2025, the company expanded its investment plans to €5bn ($5.8bn) in cloud and artificial intelligence infrastructure across Belgium over the next two years.

Google altered its plans to merge two of the buildings into a single large structure. It planned to switch from air cooling to a liquid-cooling system. The revised design would draw 600 cubic meters of water per hour from the nearby River Sambre.

The sun sets in an aerial photograph showing the construction site of a Google data centre in Farciennes, Belgium
Photo: BBC

Wallonia Minister Revokes Amended Planning Permit

François Desquesnes, the Wallonia infrastructure minister, revoked the amended planning permit in August following local opposition and concerns about severe droughts. Greenpeace criticized the continued building activity on the site. It published drone footage that showed work progressing despite the permit cancellation.

Joeri Thijs from Greenpeace Belgium said that “that Google continues to build without a permit is disrespectful to the environment, local residents, and the law,” according to DatacenterDynamics. Greenpeace said that Google’s existing data center in Saint-Ghislain uses about 1 billion liters of water annually for cooling. It returns about a quarter and evaporates the rest.

Google challenged the permit revocation before Belgium’s Council of State. A public hearing on the matter is scheduled for January 7, 2027.

Greenpeace Requests Halt to Construction Activity

Greenpeace Belgium formally requested an immediate halt in a letter sent to the Walloon administration on November 23, 2026. It pointed to satellite imagery recorded across five observation dates between August 13, 2026, and November 14, 2026. Nadia Cornejo, a Greenpeace spokesperson, welcomed the reported stoppage. She confirmed the environmental organization would continue monitoring activity at Aiseau-Presles.

A Walloon government framework published on November 12, 2026, categorizes data centres as support for artificial intelligence and cloud development. It identifies electricity, land, and water as strategic constraints.

Inspectors Visit Unauthorized Construction Site

Inspectors visited the property on November 26, 2026, to notify representatives that all building activity had to cease immediately, according to the Wallonia regional government. Nicolas Jernot, a spokesperson for the regional government, said that inspectors identified the erection of a 3-hectare structure without legal authorization.

Photo: Bangkok Post

A Google spokesperson told Agence France-Presse that they had halted works consistent with the direction from local authorities and pending additional guidance.

Regional inspectors documented that structural work on the unauthorized building was nearly complete when they served the stop-work order to approximately 300 workers on site. Raphaël Stokis told public broadcaster RTBF that inspectors observed the structure was almost finished despite the refusal of the permit.

Google maintained its position regarding local regulations as the legal proceedings advance. A company spokesperson said that “we have operated in Belgium for over 15 years and remain committed to complying with local laws,” as reported by AFP.

The dispute in Wallonia coincides with regulatory scrutiny elsewhere in Europe. Finland authorities halted work on Google data centre sites in October pending environmental impact assessments.